Belmont Sports Fields

Belmont Sports Ground revamp August 2024-5.jpg

Council has commenced works on its master plan for Belmont Sports Fields (Barton Field and Lumsden Oval).

The Belmont Sports Fields Master Plan seeks to capitalise on Council's largest sports area to develop a sports facility suitable for local sporting groups and regional-level competitions.

Barton Field and Lumsden Oval are currently utilised by four sporting clubs including rugby league, soccer, cricket and baseball. There is future potential to accommodate additional sports such as AFL.

There is an allocation of funds for a new amenities building within the Belmont Contributions Plan (OS-001), with the remainder of funding to come from grants and other funding sources.

Key features

  • Modular sports fields that can be set up to service different sporting needs and events
  • Up to seven rectangular sports field with drainage, irrigation and lighting
  • Up to two baseball diamonds
  • Up to three AFL fields
  • Up to three cricket fields
  • Three new amenities buildings
  • Cricket and baseball batting nets and cages
  • Car parks, hardstand areas, spectator seating and connective pathways

Where is the project up to?

Stage 1 construction zone.png

Above: The stage one construction zone

Stage one works are nearing completion with turf laying in its final phase and the amenities buildings almost finished.

Council awarded the design and construct contract for works on Barton 2 and Lumsden fields to pre-eminent turf services company Green Horticultural Group (GHG), who began work on the eastern fields in March.

GHG has led a host of major national projects, including turf works for the Sydney 2000 Olympics, Sydney Cricket Ground wicket replacements and reconstructing the Parramatta Eels NRL facility at Memorial Park.

A total of 11,250 square metres of turf has been laid at Barton fields with the most recent load, scheduled for 31 October, bringing completion to 95 per cent.

Lumsden fields are being graded in preparation for their turn, while concreting and fencing for the field perimeters is continuing.

The baseball diamond will take shape in November.

Field construction will run through to the end of 2024 followed by turf establishment.

While the grounds won't quite be ready for summer sports, they should be primed for a return to play in the winter with handover to clubs expected early next year.

Amenities buildings update

IMG_0535.JPG

The Barton buildings have progressed rapidly in recent weeks with solar panels installed, external painting completed, tiling almost finished and the internal partitions 80 per cent done.

Fit out for the plumbing is now underway alongside window and panel rib ceiling works.

Solar and painting are also finished at the Lumsden building, where rendering, security gates and stormwater connections have also wrapped up.

The hydraulic rough-in and Soffit sheeting are ongoing.

Unique Building Partners was awarded the building contract and established on site during April 2024.

UBP has been a high performer in the commercial and residential construction market in the Central Coast and Hunter Regions since 2014, and has worked with Council on several past projects.

Clubs will have time to move out of the existing buildings late this year prior to demolition of these structures.

No other site infrastructure will be impacted by this process.

Work on fencing, landscaping and connections will take place alongside building construction works August through October.

Electrical upgrades will be included in the scope of these works.

Consultation with user groups and sporting clubs was undertaken to inform building designs.

Concept image and field designs

Building design southeast view.JPG
Amenities building concept.

Field designs.png

Field designs for Barton and Lumsden.

Project timeline

Date
Description
2022
Stage 1 - design
2023
Stage 1 - start of construction
TBC
Stage 2
TBC
Stage 3

Updated timeline

  • Recommence field construction and site remediation - March 2024
  • Share field designs - April 2024
  • Turf laying – June / July 2024
  • Field handover – December 2025
  • Building Construction – March to November 2024
  • Demolition of Barton amenities – December 2024
  • Building handover - December 2024.
  • Next stages design and consultation – TBA (not currently funded)
  • Next stages construction – TBA (not currently funded)

Location

1A Maude Street, Belmont 2280

View in Google Maps

Google Map